The
work schedule is theoretical and based on ideal conditions. Actual
work done on any specific Saturday may vary since it is dependent
upon the weather, number of volunteers available, work done on the
prior Saturday and the schedule of Seminole County inspectors.
A typical workday
will start at 8:00 AM and end around 3:00 PM. Lunch will be provided
by volunteers. Dress appropriately and for safety. Work shoes, shorts,
jeans are the dress code of the day. Habitat provides all tools
but if you have a favorite hammer or shovel, please bring it along.
Each week, pictures
will be linked to the date of the workday. You can follow Wekiva's
progress right here.
| Saturday' Date |
Type
of Work |
| January
24, 2004 |
Groundbreaking;
install form boards |
| January
31, 2004 |
Dig
footers |
| February
7, 2004 |
Plumbing,
install steel |
| February
14, 2004 |
Masonry |
| February
21, 2004 |
Trusses/Framing
(more hands the better) |
| February
28, 2004 |
Continue
interior framing |
| March 6,
2004 |
Rough
trades, windows & trim |
| March 13,
2004 |
Roofing |
| March 20,
2004 |
Shingles
and insulation |
| March 27,
2004 |
Begin
dry wall installation |
| April 3,
2004 |
Continue
dry wall installation |
| April 10,
2004 |
Finish
dry wall; Stucco |
| April 17,
2004 |
Exterior
painting; interior trim |
| April 24,
2004 |
Interior
painting |
| May 1,
2004 |
Install
fixtures/cabinets/appliances |
| May 8,
2004 |
Interior
cleaning; driveway/sidewalk |
| May 15,
2004 |
Lay
sod; landscaping |
| May
22, 2004 |
Final
inspection |
| Dedication
Ceremony: Sunday May 23, 2004 |
|